UWIP1 GT-2 Major Overhaul

Executive Performance Summary & Data Insight

PROGRESS
100%
PLANNED DAYS
60
ACTUAL DAYS
45
15d Ahead 🎉
TOTAL TASKS
352
PERMITS
87
AVG HEADCOUNT
14
Planned vs Actual Progress Comparison
Daily Task Completion
Resource Deployment (Headcount)
Planned vs Actual Days Comparison
Work Permit Breakdown
💰 Cost Avoidance Breakdown
TitleAmount
2nd Stage Bucket Refurbishment $741,571.64
Diaphragm Casing Optimization $416,498.00
TOTAL MONEY AVOIDED $1,158,069.64
⏱️ Working Hours & Safety
CategoryRecord
Total Working Hours 8,640 Hrs
Safety Observations 0
Safety Incidents 0