UWIP1 GT-2 Major Overhaul
Executive Performance Summary & Data Insight
Control Panel
PROGRESS
100%
PLANNED DAYS
60
ACTUAL DAYS
45
15d Ahead 🎉
TOTAL TASKS
352
PERMITS
87
AVG HEADCOUNT
14
Planned vs Actual Progress Comparison
Daily Task Completion
Resource Deployment (Headcount)
Planned vs Actual Days Comparison
Work Permit Breakdown
💰 Cost Avoidance Breakdown
Title
Amount
2nd Stage Bucket Refurbishment
$741,571.64
Diaphragm Casing Optimization
$416,498.00
TOTAL MONEY AVOIDED
$1,158,069.64
⏱️ Working Hours & Safety
Category
Record
Total Working Hours
8,640 Hrs
Safety Observations
0
Safety Incidents
0